FileNorth Witney SDA / WEL2 Opened2014 Status Open — 2043 Local Plan examination & reviewed application Latest entry 26 Aug 2026
NWAG — objection lodged, since 2014

North Witney Action Group

Evidence-led objection to the North Witney SDA & West End Link Road

Get involved

The Case / Documents

The document register

To maintain credibility, NWAG has been careful to use evidence against the building of the 1,400 house NWSDA and WEL2 that has ONLY been extracted from authoritative sources — Oxfordshire County Council, West Oxfordshire District Council, Thames Water, the Environment Agency, the National Planning Policy Framework, and the North Witney (Land) Consortium itself. Every document below carries a stable reference code (e.g. EA 2007) — the same code used inline wherever that document is cited elsewhere on this site.

NWAG submissions & responses

Consultation responses, examination submissions and planning objections, 2014 – 2026.

RefDocumentDateTheme
APP·2026 Comments on the Consortium's reviewed application Aug 2026Viability
LP2043·2025 Response to questions 11 & 12, WODC 2043 Local Plan Consultation Dec 2025Viability
APP·2024 Objection to planning application 24/00482/OUT Apr 2024Traffic Flooding
LP2041·2023 Local Plan 2041 submission Oct 2023Plan policy
LTR·2023 Letter to WODC Principal Planner Jul 2023Plan policy
EIA·2023 EIA Scoping submission May 2023Flooding Traffic
LP2041-FOCUS Local Plan 2041 — Areas of focus 2023Plan policy
TW·2019 Comments on Taylor Wimpey's Parcel 2 application May 2019Plan policy
SA·2017 WODC Sustainability Appraisal consultation response Dec 2017Plan policy
STAGE3·2017 Stage 3 submission 2017Plan policy
MAINMODS·2016 Local Plan 2031 — Main modifications response 2016Plan policy
INSPECTOR·2015 Submission to the Inspector for examination May 2015Plan policy
LP2031·2014 Local Plan 2031 submission Sep 2014Plan policy
APP·2014 Response to planning application 14/01671/OUT 2014Plan policy

Statutory & third-party reports

The authoritative sources NWAG cites — cited back, in full.

RefDocumentDateSourceTheme
CIL·2024 CIL Viability Assessment — the £91.3m figure (2024 BCIS prices; NWAG update) May 2024WODCViability
S19·2022 Witney Flood Investigation Report (Section 19) Jan 2022Oxfordshire County CouncilFlooding
FLOOD·2020 2020 Flood Investigation, Witney 2020Oxfordshire County CouncilFlooding
ENRIGHT·2020 Witney Floods 2020 2020D. EnrightFlooding
TRA1·2014 Witney Development & Strategic Infrastructure Modelling (TRA1) 2014Oxfordshire County CouncilTraffic
FLOWMODEL Witney Traffic Flow Model OCC, via FOITraffic
EA·2007 Witney Flood Review, July 2007 2007Environment AgencyFlooding
KIRKHAM·2012 Kirkham Landscape & Visual Review of Strategic Site Options 2012West Oxfordshire District CouncilLandscape
FLOODV3 Flooding v3 Flooding

Consortium documents

The developers' own commitments — the standard the site must be held to.

RefDocumentDateSourceTheme
PROMISE·2009 "New Housing Development for Witney" — the "fund in full" commitments 2009North Witney ConsortiumViability
FRAMEWORK·2012 Developer Framework Document Dec 2012North Witney ConsortiumViability
COMMIT·2012 Statement of Commitment to WODC Mar 2012MeridianViability
HIGHWAYS·2012 Highways delivery trajectory Sep 2012MeridianTraffic